Q1
If the USL is 6 and the LSL is 3.5, find the Ppk when the process standard deviation is 1.2
Save your time - order a paper!
Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines
Order Paper Nowchoices are:
a) 0.735
b) 0.264
c) 1.292
d) 0.431
This question deals with finding the Ppk, which is a performance index that accounts for processes that are not centered. Of the two calculations, we assign the smaller value to PpK.
Given data are: the upper specification limit (6) and lower specification limit (3.5) for a process, the standard deviation (SD=1.2) of the process. To find the Ppk , we do two calculations:
Of the two calculations, we assign the smaller value to PpK.
The two calculations are specified as follows:
1. Ppu=(USL- Xbar)/3* SD
2. Ppl =(X bar-LSL)/3*SD
The issue is that I am stuck in finding X bar, which is the mean of the process, to do the calculation. I need help in finding the X bar.
Is there any other formula for this type of problem?