Management. Overview

Overview

This lab assignment gives you a chance to practice creating a WBS within MS Project or your chosen PM software tool. It is due at the end of Week Four.

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

Requirements

•  Create a WBS in MS Project or your chosen PM tool

Instructions

•  This lab assignment follows the construction example described in the MS Project Tutorial in your textbook, appendix B.

[NOTE:  I am NOT asking you to work through the entire tutorial in Appendix B!!!   The objective is for each student to show evidence of having selected, downloaded/installed (if necessary) a PM tool, and get your feet wet entering just the WBS into the tool.   This is a very simple assignment and should take only a few minutes once you have selected and installed the PM software of your choice.]    Please don’t over-think it.

•  Your WBS should be created in your chosen PM tool for the tasks listed below
•  Submit your document to the instructor via Canvas as an image file (.jpg, .pdf, .gif)

Notes

Imagine that you are a project manager for a construction company.  You must create a WBS for the Site Preparation phase of this project.  Here is a list of tasks.

Task Title Predecessors Duration   A Contract Approval — 5   B Site Survey A 5   C Permit Application A 4   D Grading B,C 5   E Sewer Lines B 7   F Base Paving D 3   G City Approval C,F 6   H Final Paving E,G 8

Ret

Management

Thanks for installing the Bottom of every post plugin by Corey Salzano. Contact me if you need custom WordPress plugins or website design.

"Do you have an upcoming essay or assignment due?


Get any topic done in as little as 6 hours

If yes Order Similar Paper

All of our assignments are originally produced, unique, and free of plagiarism.