Order Paper NowGiven the following information about a small project,
Task Duration Immediate
Estimates Predecessors
A 2 days None
B 5 days A
C 4 days B
D 9 days A
E 4 days B & D
F 12 days E & C
- Draw a network diagram.
- Identify the critical path, earliest start and finish and slack for each task.
- Using MS Excel, produce a Gantt chart for this project.
- What would happen if a new estimate for task D increases its expected duration from two days to six days? Would the project take longer? Would anything else change?
NOTE: Assignment will be submitted through turnitin so be careful with originality/plagiarism.
Grading Rubric | ||
Rationale | Points Avail | Points Earned |
Spelling and Grammatical Errors | 5 | |
Schedule Development Problem | ||
a. Network diagram | 15 | |
b. Identify the critical path, earliest start and finish and slack for each task. | 25 | |
c. Gantt chart for this project. | 15 | |
d. Project Change | 10 | |
Total | 70 |