Project 2.

Week 2 Project

Previous Next 

Instructions

Scheduling

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now

For an organization, the following project schedule is given. Assume that all times are in days.

TaskPredecessor

Normal

Time

Crash

Time

Crash Cost Slope

(per day)

A

None

7

7

NA

B

A

3

3

NA

C

A

8

4

600

D

A

4

4

NA

E

B

6

5

600

F

C, D

2

2

NA

G

E, F

6

6

NA

H

F

5

3

400

I

G, H

4

4

NA

J

I

2

2

NA

Address the following:

  • Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times.
  • Calculate the slack time for each activity.
  • Identify the critical path(s).
  • Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much.

Submission Details:

  • Submit your report in a three- to four-page Word document, using APA style. 
  • Submit it to the Submissions Area by the due date assigned.
  • Name your document SUO_MGT3059_W2_ LastName_FirstInitial.doc.

Project 2

Thanks for installing the Bottom of every post plugin by Corey Salzano. Contact me if you need custom WordPress plugins or website design.

"Do you have an upcoming essay or assignment due?


Get any topic done in as little as 6 hours

If yes Order Similar Paper

All of our assignments are originally produced, unique, and free of plagiarism.