Week 9 activity bus 375 | BUS 375 – Project Management | Strayer University

 

Week 9 Activity – Project Performance Measurement & Closure

Overview

With the communication issues stabilized, the focus turns to project performance measurement and closure. Chapter 13 presents a  discussion on metrics used to assess project performance. Three commonly used metrics are schedule variance (SV), cost variance (CV), and cost performance index (CPI). The sponsor is not familiar with how these metrics work and has asked for a demonstration of how they are used. The sponsor has presented a scenario and is requesting you to conduct a  demonstration using fictitious data to access the results given the following situation.

Instructions

  1. On day 51, a project has an earned value of $600, an actual cost of $650, and a planned cost of $540. Compute the SV, CV, and CPI  for the project. Present your results and explain them.
  2. Next, the project sponsor wants to be assured that the project will be closed in accordance with best practices. Research what the Project Management Body of Knowledge (PMBOK) says about closing projects and briefly discuss it.

Due By 6/5/2022 Before Midnight

Save your time - order a paper!

Get your paper written from scratch within the tight deadline. Our service is a reliable solution to all your troubles. Place an order on any task and we will take care of it. You won’t have to worry about the quality and deadlines

Order Paper Now
 
"If this is not the paper you were searching for, you can order your 100% plagiarism free, professional written paper now!"

"Do you have an upcoming essay or assignment due?


Get any topic done in as little as 6 hours

If yes Order Similar Paper

All of our assignments are originally produced, unique, and free of plagiarism.